Guide · NEMA environmental licences · Updated 2026-10-19

NEMA licences for building in Nairobi

Many projects in Nairobi need a licence from NEMA, the National Environment Management Authority, before they start — a block of flats, offices, a factory, a hospital, a fuel station. The licence follows an environmental impact assessment (EIA): a study of how the project could affect the land, water, air and people around it. Applications go online, on NEMA’s licensing system, ENVIS. Look at the site on Nairobi Maps first.

Check the site on the map Apply on ENVIS (NEMA)

Which report does your project need?

NEMA’s schedule of projects (Legal Notice No. 31 of 2019, under the Environmental Management and Co-ordination Act, EMCA) places a project at low, medium or high risk, by its type and size. The risk decides what goes to NEMA. A NEMA-registered expert screens the project and prepares the report.

RiskWhat goes to NEMA
Low riskA Summary Project Report (SPR)
Medium riskA Comprehensive Project Report (CPR)
High riskTerms of reference, then an EIA study report (SR), published for public comment

Other NEMA licences a building or business may need

LicenceWhat it is for
Environmental auditThe check on a project that is already running.
Effluent discharge licencePermission to discharge wastewater into the environment.
Air emission licencePermission to release emissions from listed facilities and equipment.
Licence transfer and variationWhen a licensed project changes hands, or changes shape.
Waste, chemicals, plastic packaging and othersAlso applied for on ENVIS, under their own regulations.

How an application moves

  1. Screen the project. A NEMA-registered expert reads the project against NEMA’s schedule of projects (Legal Notice No. 31 of 2019), which places it at low, medium or high risk. The risk decides the report.
  2. Check the site. The plot, its zone, the rivers, roads and airports around it, and what NEMA has already licensed there — on the map, before a page is written.
  3. Prepare the report. The expert describes the project and its site, consults the people and bodies it may affect, and writes an environmental management plan: how each effect will be avoided, reduced or managed.
  4. Submit on ENVIS. The report is lodged online on NEMA’s licensing system, and its fee is paid. NEMA may also ask for printed copies of a comprehensive project report or a study report.
  5. NEMA reviews it. NEMA reads the report, may visit the site and may ask for more information. It can accept the report, or ask for a fuller one.
  6. The decision. NEMA issues an EIA licence with conditions, or refuses. A decision can be appealed to the National Environment Tribunal.
  7. After the licence. Build and run the project as licensed, keep to the conditions, and keep records for the environmental audits that follow.

How long it takes

NEMA does not publish one time for every case. A summary report moves faster than a full study, which waits for its public comment period. Incomplete reports and missing documents — the title, the drawings, a change of use where the county needs one — are the usual causes of delay. Follow the application on ENVIS.

Check the site before you apply

Most of what a NEMA report describes is already on the map. Check these first:

CheckWhereWhy it matters
The plot and its numberSearch the map by LR, block or FR numberEvery report and licence names the plot. Make sure the parcel on the map is the land the project is on.
What the zone allowsIts zone page, or tap the plot on the mapA report describes the project against the county’s planning rules: floors, plot ratio, ground coverage and use.
Rivers, wetlands and riparian landThe rivers and water bodies layers on the mapWork near a river or a wetland raises a project’s effects, and can need separate consent from NEMA and the Water Resources Authority.
Airport height limitsAirport height limitsNear JKIA and Wilson, the Kenya Civil Aviation Authority can limit height below what the zone allows.
Where wastewater goesThe Trunk sewer layer, and connecting to the sewerInto a public sewer, it is agreed with the water company. Anywhere else, it needs NEMA’s effluent discharge licence.
Who lives around itThe census population layers on the mapThe expert must consult the people a project affects; the census says how many live around it.
What NEMA has licensed around itThe NEMA layers on the mapNeighbouring projects, and the emission and effluent licences near the site, are part of what the site already lives with.
The right to the landAn official search on ArdhisasaThe proponent must own the land or have the owner’s consent. Reports usually include a copy of the title.
The county’s approvalBuilding and planning approvalNEMA’s licence and Nairobi City County’s approval are separate. A project needs each one that applies to it before work starts.

NEMA licences on the map

Nairobi Maps carries NEMA’s licensing records for Nairobi as three map layers:

LayerWhat it holds
Project reportsSummary and comprehensive project reports, terms of reference approvals and study reports, with their licence variations.
Licences and permitsEffluent discharge and air emission licences, EIA licence variations and transfers, designated laboratories, and chemical and vehicle-emission-testing licences.
AuditsEnvironmental audits of running projects, low risk and high risk.

Each record carries its licence and application numbers, the proponent it was issued to, the kind of licence, and the plot or LR number where the report gave one. It sits where NEMA’s licensing system drew the site — a point, a boundary or a line. A record whose report states a position far from that site is flagged, as a prompt to confirm the plot. Applications with no drawn site are not on the map.

Use them to see whether a site already has a licence, what has been licensed around it, and where the licensed sources of effluent and emissions are. They are NEMA’s records as published; NEMA’s own system is the record of any licence. The NEMA layers are add-on layers: each is bought once, on any plan, and kept — see plans and pricing.

Reading a NEMA licence number

Every licence ENVIS issues has a number starting NEMA/ENVIS/, and the letters after it say what it is — for example NEMA/ENVIS/CPR/LIC-… for a comprehensive project report’s licence. Applications have a number of their own, in the same form.

LettersWhat it is
SPRSummary Project Report
CPRComprehensive Project Report
SREIA study report
EIA/TORTerms of reference approval
EAEnvironmental audit
EDLEffluent discharge licence
AQ/ELAir emission licence (AQ for air quality)
VLAA licence variation, after the report’s code — for example CPR/VLA
NTLNotice of a licence transfer
LABA laboratory NEMA has designated

Why Nairobi Maps is the first stop

Every NEMA report starts from the site: where it is, what may be built there, and what is around it. Nairobi Maps holds those facts for every parcel in Nairobi on one map — the plot by its LR, block or FR number, its zone worked out for the plot, survey plans, rivers and roads, airport height limits, census population, and what NEMA has already licensed nearby. The owner, the architect and the expert start from the same facts.

The whole checklist, from the title to the contractor, is in built-environment due diligence in Nairobi.

ENVIS and Nairobi Maps: which does what

Nairobi MapsENVIS (NEMA)
Find the plot and its numberYes, every Nairobi parcelNo
The zone and planning rules for the plotYes, worked out for each plotNo
Rivers, roads, airports and people around the siteYes, on the mapNo
NEMA licences on and around the siteYes, as map layersIts own records
Submit a report or an application, and payNoYes
The licence and its conditionsNoYes

Use them together: check the site here, apply there.

Questions

Do I need a NEMA licence to build in Nairobi?

Many building projects do. NEMA’s schedule of projects (Legal Notice No. 31 of 2019) lists which need an environmental impact assessment, and at what level, by the project’s type and size. A NEMA-registered expert screens the project against it and says which report it needs.

What is ENVIS?

NEMA’s online licensing system, at licensing.nema.go.ke. Since 28 July 2025 every new NEMA application is lodged there: EIA reports, effluent and emission licences, audits, waste and chemical licences, and the registration of environmental experts.

Is a NEMA license the same as an EIA licence?

For a project, yes: NEMA writes “license”, and Kenyan English “licence”. The EIA licence is what NEMA issues once it accepts a project’s report. NEMA also issues other licences — for effluent, emissions, waste and chemicals.

How long does NEMA approval take?

NEMA does not publish one time for every case. A summary report moves faster than a full study, which waits for its public comment period. Incomplete reports and missing documents — the title, the drawings, a change of use where the county needs one — are the usual causes of delay. Follow the application on ENVIS.

Who prepares a NEMA EIA report?

An environmental expert, or a firm of experts, registered and licensed by NEMA. EMCA requires it, and NEMA keeps a public register of the experts it has licensed.

How can I see whether a project near me has a NEMA licence?

Nairobi Maps carries NEMA’s licensing records as map layers, each record placed where NEMA’s system drew the site: project reports, licences and permits, and audits. Open the map at the place and switch the NEMA layers on.

Is Nairobi Maps part of NEMA?

No. Nairobi Maps is an independent map of Nairobi’s land, its planning rules and the records around them, for checking a site before you apply. NEMA decides every licence, on ENVIS.

Nairobi Maps is not part of NEMA. This guide explains the usual route under EMCA and NEMA’s regulations; requirements, fees and steps change, so confirm them with NEMA on ENVIS and with a registered expert.